Village Point Improvement District AGM: Sat Apr 11



VPID Annual General Meeting: April 11th, 2015, 1 pm at the Ag Hall.

Review of work completed in 2014 on the Community Septic fields located at Spinnaker, Quadrant and Lundy Lane. Piping, tanks, and lift stations have been replaced and upgraded to comply with Vancouver Island Health standards.

Projects under way for 2015: replacement of pipes and filtering equipment at the water treatment plant. An engineering firm has been engaged to design the new building and specify equipment upgrades required. Estimated completion: late fall 2015.

For further information please contact Renate, VPID Administrator (250) 539-2202.

posted April 2015